Modeling the Impact of Climatic and Regional Conditions on Construction Project Duration Using a Data-Driven Approach and a Two-Component Overhead Coefficient Model

Authors
1 Department of Civil Engineering, Roudehen Branch, Islamic Azad University, Roudehen, Iran
2 PhD, Associate Professor, Department of Architectural Technology (Project and Construction Management), Faculty of Architecture and Urban Planning, Art University of Tehran, Tehran, Iran
3 Department of Civil Engineering, Karaj Branch, Islamic Azad University, Karaj, Iran
10.22034/jgeoq.2026.603562.4556
Abstract
Determining the duration of construction projects is one of the important issues in project management and is a key factor affecting resource planning, contractual commitments, execution costs, and the timely commissioning of projects. In many projects, the contract duration is determined based on expert experience, similar projects, and professional judgment, which may result in discrepancies between the estimated and actual project durations. The present study aims to determine and model a time overhead factor for adjusting the baseline duration of construction projects. To this end, data from 57 construction projects implemented within the framework of the country's technical and executive system were collected, and the baseline duration of each project was determined based on the method proposed in a previous study. Subsequently, the time overhead factor for the studied projects was calculated using the ratio of the actual project duration to the baseline duration, and the factors affecting variations in this factor were investigated. In the next stage, data-driven methods and the algorithms employed in the study were used to model the relationship between the influencing factors and the time overhead factor, and the performance of the model was evaluated using statistical indicators.
Keywords

سازمان برنامه و بودجه کشور (1403)  فهرست‌بهای ابنیه. سازمان مدیریت و برنامه‌ریزی کشور.
سازمان برنامه و بودجه کشور. (1378)  موافقت‌نامه و شرایط عمومی و شرایط خصوصی پیمان‌ها و مقررات آن‌ها (نشریه شماره ۴۳۱۱). سازمان مدیریت و برنامه‌ریزی کشور.
 References
Plan and Budget Organization of Iran. (2024). Building Works Price List. Management and Planning Organization of Iran. [In Persian]
Plan and Budget Organization of Iran. (1999). Agreement, General Conditions, Special Conditions of Contracts, and Related Regulations (Publication No. 4311). Management and Planning Organization of Iran. [In Persian]
Rezaei, A. R., Barmayehvar, B., & Lork, A. (2024). Determining time for completion construction projects using time list. JES Journal of Electrical Systems, 20, 5387–5396.
Goldratt, E. M. (1997). Critical chain. North River Press.
Assaf, S. A., & Al-Hejji, S. (2006). Causes of delay in large construction projects. International Journal of Project Management, 24(4), 349–357. https://doi.org/10.1016/j.ijproman.2005.11.010
Sambasivan, M., & Soon, Y. W. (2007). Causes and effects of delays in Malaysian construction industry. International Journal of Project Management, 25(5), 517–526.
Fallahnejad, M. H. (2013). Delay causes in Iran gas pipeline projects. International Journal of Project Management, 31(1), 136–146. https://doi.org/10.1016/j.ijproman.2012.06.003
Herroelen, W., & Leus, R. (2005). Project scheduling under uncertainty: Survey and research potentials. European Journal of Operational Research, 165(2), 289–306. https://doi.org/10.1016/j.ejor.2004.04.002
Chen, L., Lu, Q., & Han, D. (2023). A Bayesian-driven Monte Carlo approach for managing construction schedule risks of infrastructures under uncertainty. Expert Systems with Applications, 212, 118810. https://doi.org/10.1016/j.eswa.2022.118810
Leach, L. P. (1999). Critical chain project management improves project performance. Project Management Journal, 30(2).
Fan, S.-L., Yeh, I.-C., & Chi, W.-S. (2021). Improvement in estimating durations for building projects using artificial neural network and sensitivity analysis. Journal of Construction Engineering and Management, 147(7). https://doi.org/10.1061/(ASCE)CO.1943-7862.0002036
Al-Attar, H., Sweis, G., Tarawneh, B., Abu-Khader, W., Haddad, L., & Sweis, R. (2025). Enhanced construction project duration estimation using artificial neural networks: Initial design and planning stages. Construction Economics and Building, 25(2), 168–191. https://doi.org/10.5130/AJCEB.v25i2.9253
A generalized artificial neural network (ANN) model for predicting construction project durations based on cost and geolocation data. (2026). Engineering, Construction and Architectural Management. https://doi.org/10.1108/ECAM-07-2025-1227
A machine learning-based framework for predicting project duration during the planning phase of highway construction projects. (n.d.).
Mirjalili, S., Mirjalili, S. M., & Lewis, A. (2014). Grey wolf optimizer. Advances in Engineering Software, 69, 46–61. https://doi.org/10.1016/j.advengsoft.2013.12.007
Storn, R., & Price, K. (1997). Differential evolution—A simple and efficient heuristic for global optimization over continuous spaces. Journal of Global Optimization, 11, 341–359. https://doi.org/10.1023/A:1008202821328
Dorigo, M., Maniezzo, V., & Colorni, A. (1996). Ant system: Optimization by a colony of cooperating agents. IEEE Transactions on Systems, Man, and Cybernetics—Part B: Cybernetics, 26(1), 29–41. https://doi.org/10.1109/3477.484436
Holland, J. H. (1975). Adaptation in natural and artificial systems. University of Michigan Press.